Dew point calculator for painting
Enter the air temperature, humidity and steel surface temperature from your gauges. The calculator applies the coating industry checks (surface at least 3 °C above the dew point and RH no higher than 85%) and tells you if you can paint now.
Can I paint now?
Move a slider or type a value. Results and the chart update as you go.
How dew point calculator for painting works?
To check painting conditions, the calculator finds the dew point from air temperature and relative humidity (RH), compares it with your steel surface temperature and applies two limits: surface at least 3 °C (5 °F) above the dew point and RH at or below 85%.
- It calculates the dew point from the air temperature and relative humidity at the work area.
- It compares the steel or substrate temperature, from a surface thermometer, with the dew point.
- It passes only when the surface is at least 3 °C above the dew point and RH is at or below 85%, the usual coating specification limits.
- The scale shows where the surface sits against the dew point and the +3 °C line.
Dew point calculator for painting formula
The painting check is margin = Ts − Td ≥ 3 °C and RH ≤ 85%, the defaults in ISO 8502-4 and most coating specifications. The dew point comes from Td = temperature where es(Td) = RH × es(T).
- T air temperature, °C
- RH relative humidity, %
- Ts steel (substrate) temperature, °C
- Td dew point, °C
- margin Ts − Td, °C (× 1.8 for °F)
Dew point calculator for painting conversion chart
The surface must be at least this warm (dew point + 3 °C) before coating. Always follow the paint datasheet if it is stricter.
| Air temp | 50% RH | 60% RH | 70% RH | 80% RH | 85% RH |
|---|---|---|---|---|---|
| 5 °C | −1.6 | 0.9 | 3.0 | 4.8 | 5.7 |
| 10 °C | 3.1 | 5.6 | 7.8 | 9.7 | 10.6 |
| 15 °C | 7.7 | 10.3 | 12.6 | 14.6 | 15.5 |
| 20 °C | 12.3 | 15.0 | 17.4 | 19.4 | 20.4 |
| 25 °C | 16.9 | 19.7 | 22.1 | 24.3 | 25.3 |
| 30 °C | 21.4 | 24.4 | 26.9 | 29.2 | 30.2 |
| 35 °C | 26.0 | 29.1 | 31.7 | 34.0 | 35.1 |
Coating inspection checklist
| Check | Typical limit | Source |
|---|---|---|
| Surface above dew point | at least 3 °C (5 °F) | ISO 8502-4, coating specs |
| Relative humidity | at most 85% | Most product data sheets |
| Surface temperature | at least 5 °C, within product range | ASTM D3276, data sheet |
| Trend | Not falling toward the dew point | Good practice |
Why paint fails near the dew point
Below about 3 °C margin, the air touching the steel is near saturation. Moisture adsorbs on the surface as a film too thin to see, and paint applied over it doesn’t wet the metal.
Morning and evening risk
Steel lags behind the air: it warms slowly in the morning and cools fast after sunset, especially on clear evenings. Plan application so the coating can cure before the surface approaches the dew point again.
Minimum surface temperature for painting
| Air temp | 50% RH | 60% RH | 70% RH | 80% RH | 85% RH |
|---|---|---|---|---|---|
| 5 °C | −1.6 °C | 0.9 °C | 3.0 °C | 4.8 °C | 5.7 °C |
| 10 °C | 3.1 °C | 5.6 °C | 7.8 °C | 9.7 °C | 10.6 °C |
| 15 °C | 7.7 °C | 10.3 °C | 12.6 °C | 14.6 °C | 15.5 °C |
| 20 °C | 12.3 °C | 15.0 °C | 17.4 °C | 19.4 °C | 20.4 °C |
| 25 °C | 16.9 °C | 19.7 °C | 22.1 °C | 24.3 °C | 25.3 °C |
| 30 °C | 21.4 °C | 24.4 °C | 26.9 °C | 29.2 °C | 30.2 °C |
| 35 °C | 26.0 °C | 29.1 °C | 31.7 °C | 34.0 °C | 35.1 °C |
Electronic dew point meter vs sling psychrometer
| Electronic meter | Sling psychrometer + chart | |
|---|---|---|
| Speed | Instant, continuous | 2–5 minutes |
| Records data | Yes, with logging | Manual |
| Surface temperature | Built-in probe on most models | Separate gauge |
| Standards | ISO 8502-4, ASTM D3276, SSPC-PA 7 | ASTM E337 |
Dew point calculator for painting FAQs
What is the 3 degree rule for painting?
The substrate must be at least 3 °C (5 °F) above the dew point during application and curing. ISO 8502-4 uses this as the default margin unless the coating specification says otherwise.
Can you paint when humidity is high?
Yes, up to a limit: most industrial coatings set a maximum of 85% RH. Moisture-curing products may allow more. Always follow the product data sheet.
How do I measure steel temperature?
Use a magnetic or contact surface thermometer on the steel, in the coldest area to be coated and out of direct sun.
Which standards cover dew point for painting?
ISO 8502-4 (guidance on estimating the probability of condensation before painting), ASTM D3276 (guide for painting inspectors) and SSPC-PA 7 for application.
What is the minimum temperature for painting steel?
Typically 5 °C (40 °F) for the surface, per ASTM D3276, but check the product data sheet.
Why does paint fail near the dew point?
An invisible film of water forms on the steel, so the coating doesn't bond to the metal. Poor adhesion, blistering and flash rust follow.
How often should I check dew point when painting?
Before starting, then at least every 4 hours and whenever the weather changes. Record readings in the inspection log.
Does the 3 °C rule apply to house painting?
Yes, as a good guide. Exterior paints need the surface dry and above the minimum temperature on the tin, and rain-free time to cure.
What is the formula for painting dew point?
The painting dew point check is Ts − Td ≥ 3 °C (5 °F), where Ts is the steel temperature and Td the dew point of the air.
What minimum steel temperature allows painting at 20 °C and 70% RH?
At 20 °C (68 °F) and 70% relative humidity the steel must be at least 17 °C (63 °F).
Which standards set the 3 °C rule?
ISO 8502-4, ASTM D3276 and SSPC-PA 7 use a 3 °C (5 °F) margin above the dew point unless the coating data sheet sets another value.